The Arizona prompt pay rules for private construction: when an owner must certify and pay a billing, what may be withheld, payments down the chain, interest, and the right to suspend work. These are original study notes for practice questions, with no link to the Arizona Registrar of Contractors, GMetrix or PSI. Legal points rest on the texts in force on January 1, 2027; interest rates and withholding caps can change, so check them in the current version of the text.
1. Under the Arizona prompt pay article, a billing or estimate for a progress payment is deemed certified and approved how many days after the owner receives it, unless the owner first issues a written statement of reasons?
A.R.S. § 32-1182(D) provides that a progress billing is deemed certified and approved fourteen days after the owner receives it, unless before that time the owner or the owner's agent issues a written statement giving reasons in reasonable detail. Seven days is the time the owner has to pay after certification and approval (§ 32-1182(A)), not the time to certify. Twenty-one days is the deadline in § 32-1183(G) for a contractor to pay subcontractors whose work was not the reason the owner withheld payment for defective work, and thirty days is the standard billing cycle in § 32-1182(A). Remember: the payment clock starts at certification, not when the billing arrives.
2. Under A.R.S. § 32-1181, "retention" is best described as:
A.R.S. § 32-1181(A)(5) defines retention as a portion of a progress payment otherwise due from the owner to the contractor that is withheld under the construction contract to ensure proper performance. A deposit with the registrar is a license bond or cash deposit, which is a licensing requirement and has nothing to do with progress payments. A subcontractor's own holdback from its suppliers is not retention as defined, and a design professional's certification fee is not a withholding from the contractor. Remember: retention is money the owner owes but holds back.
3. An owner may decline to certify and approve a billing or estimate under A.R.S. § 32-1182(D) for each of the following reasons EXCEPT:
A.R.S. § 32-1182(D) lists eight reasons an owner may decline to certify and approve a billing, including unsatisfactory job progress, defective construction work or materials not remedied, and third-party claims filed or reasonable evidence that a claim will be filed. A wish to pay later in a budget year is not a listed reason, so it cannot justify refusing to certify. Even for a listed reason, the owner must issue a written statement in reasonable detail within fourteen days after receiving the billing, or the billing is deemed certified and approved. Remember: the owner may withhold only for the listed reasons, and only after giving them in writing.
4. At substantial completion, Pinnacle Ridge Builders LLC submits a billing for release of retention. The owner declines part of it because punch-list work is incomplete. Under A.R.S. § 32-1182(H), what is the MAXIMUM the owner may withhold from retention, measured against the direct costs and expenses it reasonably expects to incur to protect itself from loss?
A.R.S. § 32-1182(H)(2) lets the owner withhold from retention to be released an amount not to exceed one hundred fifty percent of the direct costs and expenses it reasonably expects to incur because the contractor failed to complete portions of the work. The same 150% cap applies to final payment under subsection K. A progress payment is different: under subsection E the owner may withhold only an amount sufficient to pay those direct costs, in effect 100%. Seventy-five and 125 percent do not appear in the statute.
5. If an owner does not make a timely payment due under A.R.S. § 32-1182, what interest rate applies to the unpaid balance unless the parties agree to a higher rate?
Section 32-1182(Q) requires the owner to pay the contractor interest at one and one-half percent a month or fraction of a month on the unpaid balance, or at a higher rate if the parties agree. The same 1.5% rate applies to late payments from a contractor to a subcontractor under § 32-1183(H). One-half percent, one percent and two percent do not appear in either statute. Remember: a fraction of a month is charged as a full month.