Arizona mechanics' liens: who may claim one, the preliminary twenty day notice, recording deadlines, owner-occupant protection, waivers and bonds. These are original study notes for practice questions, with no link to the Arizona Registrar of Contractors, GMetrix or PSI. Legal points rest on the texts in force on January 1, 2027; penalty amounts can change, so check them in the current version of the text.
1. Under A.R.S. § 33-1008, which waiver and release takes effect only when the claimant's check has been properly endorsed and paid by the bank on which it is drawn?
Under A.R.S. § 33-1008(D)(1) and (D)(3), the conditional waiver and release forms take effect only “when the check has been properly endorsed and has been paid by the bank on which it is drawn”. An unconditional waiver and release states that the claimant has already been paid, and its required notice warns that it is enforceable once signed, even without payment (§ 33-1008(D)(2) and (D)(4)). A notice and claim of lien is the document a claimant records to perfect a lien (§ 33-993(A)), and a release of lien is what a lienholder issues after the lien is satisfied (§ 33-1006(A)). Remember: a conditional waiver works only after the check actually clears.
2. Ms. Reyes, managing member of Mesa Verde Roofing LLC, a subcontractor, signs an unconditional waiver and release on progress payment before any check is delivered, because the general contractor promises payment on Monday. The payment never arrives. What is the effect of the signed waiver?
Under A.R.S. § 33-1008(D)(2), each unconditional waiver and release must carry a notice stating that the document is “enforceable against you if you sign it, even if you have not been paid”. Because Ms. Reyes signed the unconditional form, she gave up the rights it covers for that progress payment although no money arrived. The rule that a waiver works only once the check is paid by the bank belongs to the conditional forms in § 33-1008(D)(1) and (D)(3). The statute does not make the waiver wait for the property owner's confirmation and gives no twenty-day right to cancel it. Remember: if you have not been paid, sign a conditional form.
3. A statement that purports to waive a lien claim is enforceable under A.R.S. § 33-1008(B) if it is made under a statutory waiver and release or if the claimant has:
Under A.R.S. § 33-1008(B), no oral or written statement purporting to waive or impair a claim is enforceable unless it follows a waiver and release prescribed by that section or “the claimant had actually received payment in full for the claim.” Partial payment, even half of the claim, is not enough. Serving a preliminary twenty day notice (§ 33-992.01) or recording a notice and claim of lien (§ 33-993) protects the claimant's rights; neither one makes an informal waiver binding. Remember: outside the statutory forms, a waiver binds the claimant only after payment in full.
4. Sage Flats Electric LLC recorded a lien that the law prohibits against the dwelling of owner-occupant Mr. Okafor. Mr. Okafor sends a written request for release on May 1. Within how many days of that request must the lien claimant issue a release under A.R.S. § 33-1006?
Under A.R.S. § 33-1006(B), when a lien that may not be filed against an owner-occupant's dwelling has been recorded, the person claiming it must issue a release within twenty days of the owner-occupant's written request. The same twenty-day period applies under § 33-1006(A) after any lien is satisfied. A claimant who fails to grant the release is liable for $1,000 plus actual damages (§ 33-1006(C), statute as published in 2026). Ten, thirty and sixty days are not periods in § 33-1006. Remember: 20 days to release.
5. Under A.R.S. § 33-992.01(C), a claimant must give the preliminary twenty day notice not later than how many days after first furnishing labor, materials or other items to the jobsite?
Under A.R.S. § 33-992.01(C), the notice must be given “not later than twenty days after the claimant has first furnished” labor, professional services, materials, machinery, fixtures or tools to the jobsite. Ten days is the time an owner has to answer a request for jobsite information (§ 33-992.01(J)); thirty days is how long a recipient has to return an acknowledgment (§ 33-992.02); 120 days is the recording period after completion (§ 33-993(A)). Remember: 20 days for the notice, 120 or 60 days for recording the lien.