Contract requirements, pool and post-storm repair contracts, void indemnity clauses, termite claims, advertising, building permits and solar work. These are original study notes for practice questions, with no link to the Arizona Registrar of Contractors, GMetrix or PSI. Legal points rest on the texts in force on January 1, 2027; dollar thresholds and payment caps can change: check the current text.

Written contract contents

Pool and post-storm repair contracts

Indemnity clauses and termite claims

Advertising and permits

Solar

Take the free test · full question bank and mock exams with a subscription

Sample questions (5)

1. Under A.R.S. § 32-1158, a contract between a contractor and a property owner must contain the required written information when the contract amount is:

  1. More than $1,000
  2. More than $500
  3. More than $100
  4. More than $5,000

Under A.R.S. § 32-1158(A) (text in effect on January 1, 2027), the written-information requirements apply to any contract “in an amount of more than $1,000” between a contractor and the owner of the property to be improved. The $100 and $500 figures are too low, because the statute does not reach those smaller jobs. A $5,000 threshold is too high and would leave out contracts that the statute covers. Remember: the line is MORE than $1,000, so a contract of exactly $1,000 is not covered.

2. Ocotillo Bend Remodeling LLC and homeowner Mr. Patel signed a written bathroom remodeling contract that leaves out the estimated completion date. Mr. Patel refuses to pay and argues that the contract cannot be enforced. Under A.R.S. § 32-1158, how does this argument fare?

  1. It fails unless the Registrar approves the omission in writing
  2. It succeeds, because a missing required item makes the contract void
  3. It succeeds until the contractor adds the missing date to the contract
  4. It fails; noncompliance is no defense to an action for payment

Under A.R.S. § 32-1158(C), the section's requirements are “not prerequisites to the formation or enforcement of a contract.” Failure to comply is not a defense by either party to an action for compensation, damages, breach or enforcement. The statute does not void the contract, and it does not let the owner withhold payment until the contractor cures the omission. It also requires no Registrar approval. Remember: a missing item does not make the contract unenforceable.

3. For a residential in-ground swimming pool contract with a purchaser who will live in the home, what is the MAXIMUM down payment payable on execution of the contract under A.R.S. § 32-1158.01?

  1. 10% of the original contract price
  2. 20% of the original contract price
  3. 15% of the original contract price
  4. 25% of the original contract price

A.R.S. § 32-1158.01(A)(2)(a) caps the down payment payable on execution of the contract at “not more than fifteen percent of the original contract price.” Ten percent is below the cap and is not the legal limit. Twenty and twenty-five percent exceed the cap; twenty-five percent is the limit for each later payment (after excavation, after steel, plumbing and pneumatically applied concrete, and after decking), not for the down payment. Remember: 15% down, then up to 25% at each of three milestones.

4. Desert Bloom Pools Inc. contracts with Mr. Patel, who will live in the home, to build an in-ground pool. The excavation work is now complete and there are no change orders. Under A.R.S. § 32-1158.01(A)(2), what is the MAXIMUM payment the contractor may collect at this stage?

  1. 10% of the original contract price
  2. 15% of the original contract price
  3. 25% of the original contract price
  4. 50% of the original contract price

Under A.R.S. § 32-1158.01(A)(2)(b), after the excavation work is completed the contractor may collect a payment of not more than twenty-five percent of the original contract price plus any written change orders approved by the purchaser. With no change orders, that is 25% of the original price. Fifteen percent is the cap on the down payment at signing, a different milestone, and ten percent does not appear in the pool payment schedule. Fifty percent is the down-payment cap for post-storm repair contracts under § 32-1158.02(E), not a pool payment. Remember: 15% down, then up to 25% after excavation, after steel and plumbing, and after decking.

5. Under A.R.S. § 32-1158.01(A)(1), a residential pool contract must give the purchaser the opportunity to request payment and performance bonds. Who pays the cost of those bonds?

  1. The purchaser, with no surcharge or service charge added
  2. The Registrar, from the Residential Contractors' Recovery Fund
  3. The contractor and purchaser equally, plus a small service charge
  4. The contractor, who may add a service charge to the price

A.R.S. § 32-1158.01(A)(1) says the cost of the bonds “shall be paid by the purchaser” and that the contractor “shall not charge a surcharge or a service charge.” A contractor-paid bond or a service charge added to the price contradicts the statute. An equal split appears nowhere in the section. The Registrar and the Recovery Fund have no role in paying for this bond under the statute. Remember: the purchaser requests the bond and pays its cost, and the contractor adds nothing on top.